Thursday, February 26, 2009

On the billion-peso irrigation project in Norther Samar

“Let’s finish the project on time”, RDC Chair Sarmiento tells Hanjin engineers

Calbayog City. RDC-8 Chairperson and Calbayog City Mayor Mel Senen Sarmiento on Tuesday summoned some Project engineers from Hanjin Heavy Industries & Construction, Co. (HHICC) to a meeting at the function room of I’s Plant hotel, this city. On the agenda was the catch-up plan of the NIA / Irrigation and Drainage component of the Help for Catubig Agricultural Advancement Project (HCAAP). Included in this project are the irrigations systems in Catubig, Bulao and Hagbay (all in Northern Samar).

In attendance during the meeting were Ernesto Octaviano of NEDA-8, Engr. Romeo Irinco of NIA, HCAAP Consultants Teofilo Malocse and Miguel Espaldon. HHICC was represented by Engr. Hyun Suk Shin, Deok Weon Lim and Engr. Dante Tan.

Hanjin is undertaking the billion-peso project which commenced on March 22, 2007. Its original contract amount of Php 994,391,744.00 is expected to grow as revisions come along the way. Originally expected to be finished on March 19, 2010, it is now expected to be finished by August 25, 2010, with a contract duration of 1,253 calendar days from the original 1,095 calendar days.

As per January 31, 2009 accomplishment report, the HHICC’s actual performance was at 13.8% which is way below the 15.1% cumulative target. This was among the reasons for Tuesday’s meeting.

In his message, Mayor Sermiento informed everyone that as RDC Chair, he regularly updates President Arroyo on the ongoing projects in the Region 8. Among other things, he also reiterated the President’s marching orders which “to develop Samar Island”. When finished, the HCAAP would be the first major irrigation system in Samar. The President might consider inspecting the said project anytime this year.

Hanjin’s engineers present in the meeting gave their commitment to meet the project deadline. Among other things, they cited the floods as one major cause of the delay in the implementation of the project. They also noted that the area is not easily accessible. One engineer gave the assurance that they will do their best for the project. They assured everyone of their best effort in terms of equipments and manpower. By March 2009, they will focus on the project sites at Catubig and Bulao.

The HCAAP is located in the Municipalities of Catubig and Las Navas. Its fund source is JBIC Loan PH-P221 in the amount of 5,210 million yen. Its lead agency is the National Irrigation Administration (NIA). Other implementing agencies are the DPWH, Department of Health, Department of Agriculture, the Province of Northern Samar and the Municipalities of Catubig and Las Navas. When finished, the Irrigation and Drainage Component is expected to provide a 40-thousand ton rice production output per year which translates to an incremental net farm income of 247.03 million pesos (in constant 2007 prices).

No comments: